I am new to SAP MM and I am very confused about firm zone and trade off zone logic. I have to create a test scenario where I have to release the Scheduling agreement in firm , trade off and planned zones. So if I create a SA on 26th Aug 2014 and the firm zone is 3 and the trade off zone is 15. what are the dates that I need to put in the schedule lines so that all the zones could be tested.
In other ways , what I want to know is that ..does firm zone and trade off zone depends on the date when I release the schedule lines or does it depend on the date when I created the Scheduling Agreement (SA). I am sorry for my bad English , my question might confuse some people. but please please help me.