Hello experts.
We use to convert a Planned order into a purchase requisition, using the MRP, but this is not creating a commitment automatically in the PR, we are doing it manually.
Is there any way to turn it in an automatic process?
In our case, we use the Accounting Assignment Category ‘Q’ for Project (from PS module). I don´t know if this is a relevant information.
Thanks.