I am experiencing difficulties once I try to perform MEI1/MEI2.
My case is I have created a PO today with a normal PB00 (from an Inforecord) and after I have created the PO (note the GR and IR have not yet been done) I have later today created a Condition RL01 (1%) with MEK1, for the Vendor, valid from 01.07.2010 until 31.12.1999.
Now I want to update the PO with this RL01 Condition.
Therefore I customized the following (based on input I gathered from this and other forums) IMG-activities within MM>Conditions>Automatic Document Adjustment:
1. Activate Change Pointer for Message Category CONDBI;
flagged CONDBI as active
2. Control Purchasing Document Adjustment;
Added the following:
30 RL01 Vendor Discount % 2 Pricing 44 Vendor
Now as I learn from the i(nfo)-button/Program Documentation in MEI1, besides the customizing and the fact that GR/IR must not be posted yet, I have to run RMEBEIN4/MEI4 first and from the forums I learned that I also first need to run MEI3 in case the Document index active-indicator (LFM1-BLIND) is not set in my Vendor master.
Since we have not/do not want to set this indicator, I first ran MEI3 with the following fields inputted:
u2022 Save under version = 000
u2022 Purchasing document = my test PO
u2022 Automatic document adjustment = X
u2022 Subsequent settlement = X
u2022 Name of run = u2018testu2019
u2022 New run? = X
u2022 Termination date = 20.07.2010 (=Today)
u2022 Termination time = 12:00
This goes presumibly well since I get the following message: Entries were created for 1 documents in the index.
Next I ran MEI4:
Flagged the following indicators:
u2022 Purchasing documents
u2022 Pricing Documents
u2022 Flag processed change pointers for reorganization
u2022 Flag all change pointers for reorganization
Set the Condition change date from = 01.07.2010 to 31.12.2010
Also, this goes presumibly well since I get the following message: Worklist generated successfully
Next I ran MEI1 and then the fun is overu2026
I inputted the following:
u2022 Purchase Documents: my test PO
u2022 Price Determination Type = New price determ. for changed price elements, adopt manual
u2022 Manual selection of Worklist (Documents) to Be processed = X
u2022 Delete worklist after processing = X
u2022 Maximum Documents for Each Processing Step During Asynchronous Update = 1
Then, nothing happens since I get the following message:
No documents belonging to document category Purchase Order/Scheduling Agre adjusted
Message no. NI050
Diagnosis
You have not chosen any documents of category 'Purchase Order/Scheduling Agre' for processing.
Procedure
Please check your selections.
Can anybody tell me what I am doing wrong here and how I can get this thing working?
Thanks a whole lot in advance!